Monday, March 16, 2026
Farmington, CT|Independent Local News
Development

1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set

Cupola complete, windows at 80%, new ductwork approved, and contingency steady. Sept. 9 meeting canceled; Sept. 23 at 4:30 p.m. set—then a hard-hat tour. Elevator slips; budget doesn’t. Suggested

Jack Beckett
Jack Beckett· Staff Writer, Mercury Local LLC
||4 min read

1928 Committee Moves Town Hall Renovation Forward: Cupola Complete, Windows Nearing Finish, Elevator Slips A Bit

The 1928 Committee moved briskly through approvals and progress reports at its latest meeting, closing with a unanimous decision to cancel the Sept. 9 session and meet on Sept. 23 at 4:30 p.m., followed by a hard-hat walk-through of the new Town Hall. 🛠️

Routine Business

  • Call to order and Pledge of Allegiance.
  • Minutes: July 20 minutes approved; one member noted an absence.
  • Correspondence: None.
  • Reports:
    • Chair: Work “moving along nicely,” with specific praise for the cupola and craftsmanship.
    • Town Council (Joe): Summer recess, “all quiet.”
    • FHS (Mr. Fagan): “Cruise control,” central office moving along; invoices approved as needed.

Design, FF&E, and Subcommittee Notes

  • The project is entering FF&E planning—furnishings, fixtures, equipment, and technology—with meetings expected within the next month or two so furniture installation aligns with building turnover.
  • Furniture will be a mix of new and existing items moved from the current Town Hall.
  • An interior design subcommittee previously met (Jack served). Membership and next steps will be clarified.

Construction Progress (KBE)

  • Cupola: Complete; scaffolding removed “as of yesterday.”
  • Windows: ~80% installed.
  • Cast Stone Replacement: Prep complete; stone en route; work in the next couple weeks.
  • Third Floor: Walls primed and first-coatedchair rails and window sills going in; ceiling grids to start soon, then progress downward.
  • Second Floor: Chair rails in; drywall surrounds at windows; ductwork in storage room.
  • First Floor (Gym): In-wall inspection passedinsulation going infloor inspection targeted for Friday to begin drywall.
  • New Addition: Steel and three lower roof areas complete.
  • Restrooms: New restroom forming passed inspectiondrywall hung.
  • Casework: Contractor installing corridor chair rails.
  • Windows Replacement Scope: “All” except several half-rounds.

Contractor coordination requests: Early notice for end-user requirements, FF&E deliveries, and elevator access for inspections once ceiling grids are in.

Elevator Timing

  • Original install target: Sept. 25.
  • Update received before the meeting: A delay of a couple of weeks is likely; the team has not yet accepted the push.
  • Recovery plan: Nights/weekends work to maintain overall schedule. In the meantime, stairs remain in service. 🧗

Financials, Contingency, and Change Orders

Budget & Contingency

  • Routine updates to line items and contingency logs.
  • Contingency used: ~46%.
  • Forecast of pending items: $68,333.31 (subject to change).
  • Contingency remaining (including forecast): $314,849.59.

Invoices Approved

  • Silver Petruzzelli (Architect): $23,077.78 for services through July 31.
  • IMTL (Materials Testing): $1,885 (reviewed by Mason).
  • J.I. Belluccio (Site Work): Two applications: $59,897.50 and $32,852.90.
  • KBE (Application #6): $1,718,911.59 (internally reviewed and architect-approved).

Change Orders Approved

  • Basement infills following boiler removal and prior ductwork abatement: $4,106.54.
  • Storm drainage increase (gym roof) from 4-inch to 6-inch: $8,000.
  • Arc-fault breaker (state fire marshal/vault requirement): $1,039.50.
  • HVAC ductwork—shift to all new system rather than mixed new/existing: $62,481.10.
    • Note: Multiple site meetings, calls, and reviews preceded this figure. The team emphasized better long-term value and elimination of testing/inspection complications on old fire dampers.
  • Dome substructure repairs discovered under the copper during removal; Elite rebuilt in ~2.5 days$11,514.88.
  • Handrails in stairwells retained and refinished rather than replaced: credit of $6,888.80.
  • Wall thickness increase to match conditions: $3,044.55.
  • Additional precast stone replacement (approximately 20 stones, largely under windows) to avoid future failures: $21,600.

Community Updates and Communications

  • Staff will prepare a photo-driven project update for the October Town Letter; a cupola shot is requested. 📸
  • Interior colors exist; finalization is “top secret” for now.
  • Cast stone swapping to begin “in a couple/three weeks.”

Next Meetings

  • Sept. 9: Canceled.
  • Sept. 23 at 4:30 p.m.: Regular business followed by a site tour of the new Town Hall. Hard hatsrecommended. Some members will be out of town; quorum expected.

Sponsor Note (Read with a grin)

This reporting is brought to you by Farmington Storage—the place you call when your basement finds out the cupola is done and demands its space back.
Address: 155 Scott Swamp Road, Farmington, CT • Phone: 860.777.4001 • Web: farmingtonstorage.com
They won’t install your elevator, but they will store your dignity while you take the stairs. 😎


About the Author

Jack Beckett drinks coffee the way ceilings take paint—first coat early, second coat before noon, punch-list by 3. If you see him near the cupola angle-hunting, he’s fine; he’s chasing daylight and an espresso.

Find more on our site: long-form explainers, committee indices, and practical guides—all without pop-up whack-a-mole. Browse our editorial work at Editorial, learn who we are at About The Farmington Mercury, and tag along with education, zoning, and HDC coverage: Farmington High SchoolZoningHistoric District Commission. Shopping? See For Sale. Jobs? Try Positions Available. Law-and-order reader? Visit Law Enforcement. Our wetlands are lively too: Wetlands Committee. Subscribe at The Farmington Mercury — Subscribe. Questions or news tips? Contact Us. And yes, you can always message us on X/Twitter (Twix) at @WeFarmington. 💬


Stay Informed with The Farmington Mercury

Subscribe for steady reporting on meetings, budgets, and decisions that shape the town—no tracking detours, no breathless hype. Start here: Subscribe.


After-Everything Links (because you asked nicely)


Creative Commons License

© 2025 The Farmington Mercury / Mercury Local
This article, “1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set,” by Jack Beckett is licensed under CC BY-ND 4.0.

“1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set”
by Jack BeckettThe Farmington Mercury (CC BY-ND 4.0)

Jack Beckett
Jack Beckett

Staff Writer, Mercury Local LLC

Staff writer for Mercury Local covering government, elections, public safety, and development across multiple publications. Beckett has filed more than 600 stories on local policy, crime, zoning, and civic accountability in Connecticut and the Carolinas.

More in Development